Mourne Wall restoration progress allows earlier start on Slieve Donard repairs | Newry News Today

Posted by
editor@newrytimes.com
Friday, November 18th, 2022
Community

The NI Water Mourne Wall Restoration Project team is making good progress with the £2.5m phase two schedule of repairs and plans to start works on Slieve Donard this month.

 

Mourne Wall restoration progress allows earlier start on Slieve Donard repairs | Newry News Today - todays news in newry

 

The construction team led by GEDA and encompassing local stonemasons from Thomas Rooney & Sons has completed more than 65 repairs on Slieve Muck and Slievenaglogh South since August.

“And as a result of mild weather conditions will move to Slieve Donard earlier than expected.

Speaking about the work, Michael Donnelly, Senior Project Manager with NI Water says “The stone for the repairs on Slieve Donard has been bagged and is sitting in Binnian Quarry ready to be transferred by helicopter to the required locations on Slieve Donard.

“With favourable weather conditions presently, the team plans to start transporting the bagged stone and getting repairs on Slieve Donard underway in November.

“NI Water would ask the public to be mindful of the ongoing work to restore the 100-year-old Mourne Wall and the possibility of helicopters being in the area for a short period.

 


Tall Paul Marketing - NI blog content writer

 


 

“As always, any helicopter lifts will be carefully managed, with stewards and signage in place for health and safety purposes.”

“As this important project continues, I would like to thank Mourne Heritage Trust, NIEA, National Trust and the Trustees of Mourne for their ongoing guidance and assistance and acknowledge the strenuous efforts exerted by the contractors and wider project team in carrying out this vital work.”

Around 75 repairs have been identified for the section of wall on Slieve Donard with work expected to take around 6-8 weeks depending on the weather.

At the heart of the phase two programme of repairs – being managed on behalf of NI Water by RPS – is a proactive ‘stitch-in-time’ approach which will see the careful dismantling and rebuilding of vulnerable bulges in the 22mile-long wall to aid its longevity.

 


Keep up to date with all the latest Newry news, what’s on Newry, News in Newry and Mourne, and Today’s Newry News Now HERE.


 

Comment using your Newry Times/WordPress account

-->

This website does not share personal information with third parties nor do we store any information about your visit other than to analyze and optimize your content and reading experience through the use of cookies. You can turn off the use of cookies at anytime by changing your specific browser settings.

We are not responsible for republished content from this blog on other blogs or websites without our permission. This privacy policy is subject to change without notice and was last updated on 16/01/2017. If you have any questions feel free to contact Newry Times by emailing editor@newrytimes.com

Log in